Client: MOG, Mellitah Oil and gas Date: week 48 - 2017 Carry on with Engineering phase of the project, 40% of engineering work had been completed.
Upgrade of Crude Oil Heaters Control System
Ridats2018-05-04T16:57:59+00:00Client: MOG, Mellitah Oil and gas Date: week 49 - 2017 Carry on with Engineering phase of the project.
Upgrade of Crude Oil Heaters Control System
Ridats2018-02-27T17:47:39+00:00Client: MOG, Mellitah Oil and gas Date: week 52 - 2017 Carry on with Engineering phase of the project.
Upgrade of Crude Oil Heaters Control System
Ridats2018-02-27T17:24:53+00:00Client: MOG, Mellitah Oil and gas Date: week 01 - 2018 Carry on with Engineering phase of the project.
Upgrade of Crude Oil Heaters Control System
Ridats2018-02-27T13:35:52+00:00Client: MOG, Mellitah Oil and gas Date: week 50 - 2017 Carry on with Engineering phase of the project.